Meeting documents
- Meeting of Cabinet, Tuesday, 27th June, 2017 4.30 pm (Item 9.)
Minutes:
The
Cabinet considered a report providing an update on the Amersham Multi Storey
Car Park Development Project which sought approval of the final business case,
amended capital programme and confirmation on the contracts for construction.
The proposed project would provide a total of 1,046 car park spaces, resulting
in an increase of 366 spaces. The additional parking spaces from the project
were required in order to meet the increased demand for parking and were
supported by a detailed business case that had been developed, as required by
the Council’s financial strategy, using realistic and prudent assumptions on
potential income and expenditure. The proposed project was considered important
to meet the parking needs and would also help generate additional income.
The report
was considered by the Resources Overview Committee on 21 June and the
Committee’s comments were noted by the Cabinet.     A
number of questions had been raised by the Committee, and further clarification
on the pre-construction costs, total overall costs and parking charges in
relation to annual inflation, had been requested. A number of additional
questions were also raised by Committee Members following the meeting. A
supplementary appendix was circulated at the meeting responding to those
questions raised.
A number
of options had been considered in order to meet parking needs. The proposal set
out in the report, which took into account the parking needs and financial
implications, and was considered the best option. It was confirmed that Pick Everard, an independent consultant, had provided cost
certainty on the proposals. During the budget setting process the impact that
the proposed project would have on the Council’s Medium Term Financial Strategy
and treasury management strategy had been taken into account.
Interest
rates were at a historic low and in light of this it was therefore sensible to
consider borrowing to finance the project which would provide long term
benefits to the Council. The risk that the cost of borrowing could change was
mitigated through the use of a 40 year fixed rate loan from the Public Loans
Board to finance the construction costs.
Another
risk was that income from the car park would be lower than estimated. The
demand for parking spaces was subject to change however the car park was
already at full capacity and demand was unlikely to reduce in the medium term.
An extra 366 parking spaces, as proposed, would enable the car part to operate
at 85% capacity. This was the maximum number of spaces that could be provided
on that site and included the creation of an additional deck. A lower than
anticipated level of income was not therefore considered a significant risk. It
was confirmed that the income forecasts for the project were based on cautious
estimates of increased usage, and although no detailed analysis of the impact
from higher levels of income had been undertaken, this would only benefit the
project.
The
Council could also change car park prices, and a 3% increase had been included
in the business case. Car park prices were due to change later this year and
would still remain lower than competing car parks. One of the suggestions from
the Resources Overview Committee was that the business plan should show charges
being increased every 3 years, rather than annually, and the tabled appendix
included details of the financial effect of this.
At the
invitation of the Leader Councillors J Gladwin, D Phillips and P Jones
addressed the meeting. It was advised that although there was agreement that
Amersham required additional car parking there was concern regarding the
following key issues:
·
There
was uncertainty regarding the impact of parking displacement arising from an
increase in parking prices and changes to on-street parking restrictions, such
as additional no parking areas.
·
It
was suggested that parking fees, when increased, be rounded up to a practical
whole number
·
There
was also concern that a 50p increase in parking charges each year would not be
realised
·
There
was concern about the impact on demand arising from additional spaces being
created in Sycamore Road and King George V House car parks
·
It
was suggested that relaying the surface on the top floor of the car park be
shown as a separate project
·
It
was recommended that the figures in the business case be reviewed again
particularly in light of the risk of higher interest rates.
·
Further
clarity was requested in relation to the pre-construction costs and initial
design costs.
·
Concern
was raised regarding the potential increased cost arising from the risks
identified by Pick Everard such as archaeological
remains, Transport for London, and other contingencies. It was considered that
the likelihood of these having any material impact was low.
·
It
was suggested that a proportion of the Council’s reserves be used to lower the
level of borrowing required particularly in light of the low levels of income
from Council investments.
Regarding
the pre-construction costs it was confirmed that these had increased from
£591,000 to £617,000 with cost certainty and any further variation would now be
the contractor’s risk. The £110,000 initial design costs were also included
within the pre-construction cost.
The
relaying of the surface on the top floor had been included in the project costs
because it was more cost efficient to carry the work out at the same time. This
could be included as part of contract but listed as a separate project cost for
the purpose of the business case.
Regarding
the impact from extra spaces provided elsewhere, it was noted that this was
difficult to model due to the number of different factors; however the overall
effect was estimated to result in around half of the number of staff parking in
Sycamore Road temporarily during the construction of the car park.
It was
clarified that the Council’s reserves were allocated for a variety of different
schemes and it was not considered desirable to commit a significant proportion
of the reserves to a single project where alternative funding was available.
The budget setting process had taken this into account. The Council was also
gaining cost certainty through the use of a 40 year fixed rate loan.
The
Council’s Constitution required that any applications submitted by the Council
be considered by the Planning Committee and Full Council. The Planning
Committee meeting on 22 June considered the planning application relating to
the project and agreed to recommend to Full Council that the Council’s own
planning application relating to the Multi Storey Car Park be approved, subject
to amendments to conditions 2 and 13. Reference was made to the amendments made
by the Planning Committee and the costs associated with the amendments relating
to the total landscaping scheme.
Following
the discussion, the Cabinet then
RESOLVED -
1.        That the current
position of the Amersham Multi Storey Car Park Development Project be noted.
2.        That the final
business case for the project be agreed.
3.        That, subject to
the decision of the Planning Committee that the Head of Environment, in
consultation with the relevant Portfolio Holder and Director of Services, be
authorised to conclude the delivery agreement between Balfour Beatty and the
Council for the construction phase.
4.        That the Head of
Finance be authorised to carry out the necessary arrangements to obtain the
loan finance.
5.        That the Head of
Environment be authorised to negotiate and conclude any necessary agreements to
allow the development to proceed through to completion.
6.        That the 2018/19
revenue budgets include the additional revenue operating costs of a larger car
park operational from September 2018.
7.        To note and agree
that the cost of the pre-construction costs have increased from £591,000 to
£617,000 for delay due to planning and Scape fees.
AND RECOMMENDED - |
|
8. |
That £10,800,000 be added to the capital programme for the construction of
the project. |
Supporting documents: